It has been a while since my last update. Let's rewind my life events back to the time when we had the kitchen's backsplash installed. Ducky went to Kansas City on July 22. I went to Sunrise home on Thursday July 25 and the contractor came to do the backsplash template on Friday July 26. I then went back to Marietta to continue to purge and pack stuff back to Sunrise again on Tuesday August 6. Then, the crew came to install on August 7 but they could not continue due to the lights under the cabinets. Mike came to take the lights out first on Friday August 9. I went back to Marietta on Thursday August 8 and yep to purge and to pack stuff back to Sunrise again on Sunday August 11. Finally, the backsplash got installed on Wednesday August 14. Hooray! It's so beautiful! I went back to Marietta the following day. Mike came to install the lights under the cabinets on Friday August 16. Oh My! It had taken almost 1 month to complete the kitchen backsplash project. 😉
Pictures taken right after it got installed! Beautiful!